Zhangbin Water Surface Solar Power Plant Construction Project-Equipment Platform Project

Zhangbin Water Surface Solar Power Plant Construction Project-Equipment Platform Project

Construction Period:

Start Date:June 20, 2019; Contract Completion Date:September 24, 2020 

Location:

The project is located in the Lunwei East area of Changbin Industrial Zone 

Project Cost:

Approximately NT$ 670 million 

Project Description

This project is located in the Lunwei East area of Changbin Industrial Zone. It mainly involves the construction of a new bridge with a total length of 1,412.8 meters. The entire bridge is built over the sea, and the construction and transportation routes are planned to establish a construction gantry bridge of equal length and construction platforms perpendicular to the gantry bridge. Construction work starts from Bridge A1 and proceeds sequentially to install the gantry bridge and construction platforms until Platform 58.