Taichung life circle No. 2 Line East Section

Taichung life circle No. 2 Line East Section

Construction Period:

Original Contract Completion Date:November 23, 2010
Extended Completion Date:October 24, 2011 

Location:

This project is located in Beitun District of Taichung City and Taiping District of Taichung County 

Project Cost:

Approximately NT$ 2.89 billion 

Project Introduction

This project is located in Beitun District of Taichung City and Taiping District of Taichung County. The route starts near the intersection of Junfu Road and Songzhu Road (STA.4K+608) and ends near the intersection with Yucai Road (STA.7K+482) . The project scope covers a distance of approximately 2,874 meters. The main construction contents of this project include the road works of the underpass, mainline viaduct, ramp bridge, box culvert, retaining wall, sound barrier, traffic signals, lighting, landscaping, and Taipower pipeline.